| January 1: Continued work on riveting structure, right lower side skin attached. Riveted F-01412 bulkhead to aft bottom skin and attached this skin to the remaining structure. |
| January 2: Extensive riveting (mostly backriveting) of skins to bulkheads. Used MK-319-BS and MK-321-BS in some areas where reach of the called out rivets made for smaller shop heads or rivets were very hard to buck. A few "oops" rivets needed and a couple of skin dings where rivet partner (KLB) and I miscommunicated. |
Tuesday, January 3, 2017
January 1-2 2017 Update: lower side skins
Subscribe to:
Post Comments (Atom)
-
I attended Synergy Air's fundamentals class on September 10th. Completed a practice project. This was a very good learning experience...
-
I decided to go with Archer antenna for VOR/ILS - installed in the right wingtip. I had to remove 5 nutplates, match drill antenna to fit...
-
Got quite a bit done. First, I've been cleaning up wiring, putting shrink wrap over wires where they might chafe, adding cable ties, j...