December 12:
-->
Received the replacement root rib for left elevator (second one I'm building). Dimpled it, clecoed it to the other parts and drilled it for the elevator horn and the gusset. Primed it and will be ready for assembly when I have some time. |
December 16:
-->
Replacement left elevator sections 9-16 through 9-21 completed. |
December 20:
-->
Left elevator trailing edge riveted with ribs in place using proseal. Extensive prep parts for section 10. |
December 21:
-->
Parts prep section 10 - deburring, dimpling, scuffing (prep for priming) |