Monday, January 1, 2018

End of 2017 Update - starting on QB wings

Since the last update I received QB wings and have started work on the left wing.

Before starting wings I wrapped up the vents.  Not a big job but I made one decision (after checking with Van's) to make a small change - I decided to rivet the vent brackets in addition to using silicone adhesive.  I match drilled two holes in each bracket and then dimpled them: easy on the brackets but on the fuse side skin I had to use special dimple dies that pull a nail through to set the dimple.  


On to QB Wings:  First, I've inspected as much of the wing as possible, comparing the plans to what I see and checking work.  For the most part, work is very good.  I've found some rivets on the left fuel tank at the inboard rib to skin joint that I'm not impressed with, but I'm worried about replacing those since this area is sealed.  Will discuss with Vic Syracuse - if he says to replace these I will, using sealant obviously.

One of the first actual construction things I did was pages 17-04 and 17-05.  I installed the access hatch doubler (after the obligatory deburr, scuff, prime, dimple, using nutplates etc.   Looks very nice.   I also installed the landing light brackets - before doing this I primed inside the rib bay where the landing lights will be with black primer.   I countersunk and placed rivets in the two holes that are normally used to install the stall warning horn: I will be using AOA as part of my pitot tube setup so won't need the duplicate stall warning.

Next I fabricated the landing light lens and backing plates.  Fit is good but with a small gap at the leading edge - despite lots of effort to pull this flush during match-drilling.  I'll live with it and seal later after permanent installation of the landing lights.

I removed the left fuel tank after fabricating plywood forms and installing these on bench - will stay off wing until work is complete.

Last few days I worked on aileron actuation - fabricated the pushrods, installed aileron bellcrank, and fabricated the torque tube assemblies for both wings.  I'll hold off a bit on installing all this until fuel tank is back on wing and after installing the wiring/tubing in wing.

Today I bent the wire for the fuel sender float - after quite a bit of tweaking I'm happy with the fit and I went ahead and installed the sender, after testing resistance range. I used an "endoscopic" camera that connects via wifi to my ipad to inspect the positioning of the float and assure no interference with rib or vent line.  I verified electrical connection to airframe after installation - one of the screws that is used on the sender has a lock washer to ensure electrical connection.  Also installed plug in upper hole, fuel strainer/drain, and fuel pickup/strainer.















Saturday, November 25, 2017

November 2017 Update - Section 35 complete

Not as much done since last update as I would like, but I've completed section 35.  One source of delay was self-induced:  I didn't like the way match-drilled holes on the upper forward skin turned out so I replaced the skin, with all the expected issues that come with that - shipping time, skin edge prep, deburring, dimpling, priming, etc.

It turned out great and I finally have completed all riveting of the upper forward skin, attachment of the canopy hinge mechanism and mechanism for canopy release.

Next I'll wrap up end of section 29 (vents) and move on to QB wings which are sitting in the garage ready to go...





Monday, October 16, 2017

October 16th Update - Upper FWD Fuselage

Since the last update I have made substantial progress in section 35 - upper forward fuselage.  Much of this time was spent doing the usual prep of parts.   In the last few days I have completed the subpanel and am now working on preparation for riveting the upper forward skin.   I've also fabricated the pushrods for the canopy eject mechanism.  I don't plan to install the full mechanism but I will have the structure in place should I (or a future owner) decide to install the final part in the panel.  I also think having the structure there will make it easier in the future to remove the canopy for maintenance.














Monday, September 18, 2017

September 16th update - brakes and rudder pedals

Completed installation of brakes/rudders with Berenger master cylinders and TS Flightlines brake lines in fuselage, including installation of the brake fluid reservoir.

Looks really nice!



Friday, September 15, 2017

September 15 Update - working on Section 33 Brake and Rudder systems

I've been slowed down a bit by Hurricane Irma, and waiting for some parts to be shipped and also for brake pedals to be powder coated.

I've assembled the brake/rudder pedals, installed Berenger master cylinders, and partially installed brake crossover lines, lines to reservoirs, and lines from master cylinders to gear leg braces.

Beautiful products from TS Flightlines and Berenger.







Saturday, September 2, 2017

Section 31 Complete

Section 31 is the easiest of all.  The only thing that's hard is installing the fuel line brackets.

It would be MUCH harder if I actually had decided to fabricate all the fuel lines.  But I ordered all the lines from TS Flightlines, including a braided stainless steel coated teflon line from fuel pump to firewall.  Really nicely made, perfect fit.









Friday, September 1, 2017

Update September - completed section 29 (FWD MID FUSE SIDE STRUCTURE), on to section 31 (Fuel System)

Much has happened since last post.  I have completed the riveting of side skins, and all the root fairing attach angles.  I also completed assembly of the seat back brace with its adjustment guides and angles.  Finally, after riveting this brace, the gussets, and intercostals in place, I bolted in the roll bar bases.

I am skipping section 30 - where the fuselage and tailcone/aft fuselage get joined up - until I have completed as much of the systems installation in the fuselage as possible.  It will be that much harder to do these steps when I have more weight and bulk to move around, not to mention the space issue.

I ordered Berenger brake master cylinders, brake lines, and fuel lines from TS Flightlines.  Very nice stuff, and it makes the work of installing fuel/brake systems much easier, plus the Berenger wheels and brakes are better quality, lower weight than the standard stuff.

Today I installed the fuel line brackets, fuel selector, fuel pump, fuel filter, and the fuel line from selector to fuel filter/pump assembly.

Section 31 will go very quickly, then on to rudder/brake installation.  I'll wait to do the baggage floors until after joining up the fuse to tailcone.