Completed prep and primed all parts for right elevator. Completed riveting of left elevator including trailing edge and close out tab. Completed sections 9-14, -15, -16 for right elevator. Using MK-319-BS rivets for attaching skins to rear spar, much easier and less bending of skins than using the special bucking bar. Ordered more to have adequate quantity. Also ordered more 3-3 rivets for skin to ribs (not enough to completed bottom and top skin back-riveting. |
Monday, November 21, 2016
November 20, 2016: right elevator parts prep, priming, complete riveting left elevator