Received 3-3 rivets for skin riveting and more MK-319-BS. Completed most riveting of right elevator, installed foam ribs and trailing edge using proseal, clecoed trailing edge, and placed with weighted board for a few days for proseal to cure. Completed additional work on left elevator including connecting molex connector on the trim motor and rolling leading edge - clecos placed. Applied silicone sealant to connections and some shrink wrap to the wires from the trim motor. |
Monday, November 28, 2016
November 27, 2016: right elevator riveting, left elevator trim motor
Subscribe to:
Post Comments (Atom)
-
I attended Synergy Air's fundamentals class on September 10th. Completed a practice project. This was a very good learning experience...
-
I decided to go with Archer antenna for VOR/ILS - installed in the right wingtip. I had to remove 5 nutplates, match drill antenna to fit...
-
Progress is slow right now thanks to work travel interrupting my airplane building. I've been working on avionics. Finished the cent...