Completed Section 9-9 (left elevator) - including countersinking of left elevator trailing edge using special countersink from Cleaveland Tools . Extensive prep (deburring, scuffing, dimpling, priming) of all parts of the left elevator except skins). Completed (left elevator only where appropriate) sections 9-11 and 9-12, and 9-13 up to step 5.
Subscribe to:
Post Comments (Atom)
-
I attended Synergy Air's fundamentals class on September 10th. Completed a practice project. This was a very good learning experience...
-
I decided to go with Archer antenna for VOR/ILS - installed in the right wingtip. I had to remove 5 nutplates, match drill antenna to fit...
-
Got quite a bit done. First, I've been cleaning up wiring, putting shrink wrap over wires where they might chafe, adding cable ties, j...